Project title |
SAP Implementation Strategy Study |
Client |
Dolphin Energy Limited |
Year |
2003 |
Number of consultants |
4 Senior SAP Consultants |
| Scope of Work |
The objective of this project was to define key implementation elements, in terms of:
Strategy,
Approach,
People,
Project management,
Phases,
Schedule and cost.
At the end of the study, Dolphin had a clear, detailed understanding of:
Complete SAP project implementation cost and time required,
Platform technical evaluation and selection (Oracle with Unix vs. SQL with Windows),
The resources needed for each phase from the contractor and Dolphin,
The benefits of alternative contracting approaches (i.e. lump-sum against in-house with body shop resources).
The study resulted in a Project Charter, including the following activities:
Implementation scope,
Interfaces,
Implementation strategy,
System architecture and technology,
Operating system and database selection,
System authorization,
Project constraints,
Project assumptions,
Project management approach,
Implementation plan,
Resource plan,
Risk assessment,
Estimated implementation cost,
Tendering approach.
|
Rise
Project title |
SAP Detailed Scoping Study |
Client |
Dolphin Energy Limited |
Year |
2003 |
Number of consultants |
3 Senior SAP Consultants |
| Scope of Work |
Conduct an SAP To-Be Design Study resulting in a Business Blueprint, providing DEL with a general understanding of how its business processes should be mapped to SAP systems. |
The purpose of the Business Blueprint is to document in detail the scope of business scenarios, business processes and process steps, as well as taking into consideration the requirements of SAP Business Suite implementation. SAP Business Suite, including the following modules:
Financial Accounting
Controlling
Treasury
Material Management
Project Systems
Enterprise Portals
Business Warehouse
The study was conducted using SAP IDES system to demonstrate existing SAP functionalities and how they can be mapped to Dolphin's business processes. CIC provided the following deliverables to DEL :
Organizational Structure
Business Processes Master List (BPML)
Master data Requirements
Change Request Database
Interface Requirements
Reports Requirements
Enhancement Requirements
Conversion Requirements
Forms Requirements
Implementation Methodology
|
Rise
Project title |
DEL Post |
Client |
Dolphin Energy Limited |
Year |
2004 |
Number of consultants |
3 Senior Consultants |
| Scope of Work |
Build and Implement Dolphin's internet job publishing and posting application. |
This allowed job opportunities to be published, and interested applicants to apply for job offers through Dolphin Energy's web site. The project included the following:
Installation of Oracle application server / Oracle DB,
Developing Forms and Reports submitted by Dolphin using JDeveloper9i,
Technical Documentation.
|
Rise
Project title |
SAP Implementation, Phase 1 |
Client |
Dolphin Energy Limited |
Year |
2004 |
Number of consultants |
12 Senior SAP Consultants |
| Scope of Work |
Phase 1 high-level functional scope, including: |
Financials ( GL , AR , AP),
Treasury (CM, Bank Accounting),
Controlling ( OM ),
Enterprise Controlling (PSA),
Project System,
Material Management (PUR, PRO, IM),
Enterprise Portal,
Business Warehouse,
Other (AC, BC),
Supplier Relationship Management.
|
Rise
Project title |
Dolphin Portal |
Client |
Dolphin Energy Limited |
Year |
2003 |
Number of consultants |
4 Senior Consultants |
| Scope of Work |
Dolphin Energy was planning to implement Oracle 10g Portal. The requirements for the portal were as follows:
Links to corporate information, based on employees' positions and interests
HR reports published according to employee identity
A Duty Travel Request (DTR) form for employees' use
A single point of access to business reports and applications
CIC's scope was to build the portal. This included:
Installing Oracle application server/Oracle portal ,
Building the following customized Portlets:
HR and payroll reports,
Timesheet,
Attendance,
Helpdesk,
Appraisal,
User/technical documentation
|
Rise
Project title |
SAP implementation, phase 2 ( Doha , Qatar ) |
Client |
Dolphin Energy Limited |
Year |
2005 |
Number of consultants |
15 Senior SAP Consultants |
| Scope of Work |
Phase 2 high-level functional scope, including: |
Financials ( GL , AR , AP, PSA, JVA),
Assets (AA),
Controlling ( OM , PC, PA),
Enterprise Controlling (PCA),
Treasury (CM, Bank Accounting),
Integration,
Sales & Distribution,
Material Management (PUR, PRO, IM, WM, Cataloging – Requisite),
Plant Maintenance,
Quality Management,
Production Planning,
Project Systems,
Other (AC, BC, Reporting).
|
Rise